We are hoping for the following TIMELINE to occur:
1. Douglas County Deemed Design Review Complete and accepted application
- July 2007
2. Close Escrow on Land - August 2007
3. Town Board Approval (with Conditions) - August 2007
4. Major Variance (Loading) County Commission Meeting - September
2007
5. Engineer Start - Land Dev Plans - August 2007
6. Architect Start - Buildings - August 2007
7. Land Development - Approved CD's - County Planning - February
2008
8. Land Development - START - October 2007
9. Land Development - Completed & Signed Off - May 2008
10. Pad Sales - Close of Escrow - Summer 2008
11. Vertical Retail Buildings - Approved CD's - Spring 2008
12. Vertical Retail Buildings - Start - Summer 2008
13. C of O & TI Complete - Retail Buildings - Summer 2009